service to potential new customers – the Summit project
        
        
          involves installing more than 2 million ft (609 600 m) of
        
        
          6 in. (15.2 cm) HDPE natural gas pipe through some of the
        
        
          densest rock found anywhere in the US. When complete,
        
        
          this extensive pipeline network will provide natural gas
        
        
          to the towns of Gravois Mills, Laurie, Sunrise Beach,
        
        
          Camdenton, Osage Beach and Lake Ozark, Missouri.
        
        
          More than 30% of the pipeline – approximately
        
        
          600 000 ft (182 880 m) – is being installed by horizontal
        
        
          directional drilling (HDD) technology. The largest and
        
        
          most costly components of the Summit project – three
        
        
          trenchless bores beneath the lake at sites alongside the
        
        
          three major bridges in the area: the Community Bridge,
        
        
          Hurricane Deck and Niangua – were also the most visible
        
        
          and challenging. Lone Star Directional Drilling, based in
        
        
          Clarksville, Texas, was selected by general contractor
        
        
          J.F. Construction Services, based in DeWitt, Missouri, to
        
        
          complete the bores. John Dagenhart, founding partner of
        
        
          Lone Star Directional Drilling and a 20-plus year veteran
        
        
          of HDD, explains the rationale for selecting the Vermeer
        
        
          D1000x900 Navigator® horizontal directional drill for the
        
        
          challenging lake-crossing bores.
        
        
          “We’re using the D1000x900 drill for many reasons,”
        
        
          Dagenhart says. “For a maxi drill, the D1000x900 drill is
        
        
          a relatively easy system to operate…and it’s powerful.
        
        
          The drill is also very durable and reliable, which is
        
        
          important given the complexity and the length of the
        
        
          three lake crossings. We knew the D1000x900 drill had
        
        
          the capabilities to effectively power through the rock. But
        
        
          because of the intricate complexity of the lengthy bores,
        
        
          accuracy and durability are also critical.”
        
        
          High visibility; strict tolerances;
        
        
          environmental sensitivities
        
        
          Dagenhart recalls the first visit he made to the lake with
        
        
          Jim Frock, founder of J.F. Construction Services, to survey
        
        
          the new Summit project installation route.
        
        
          Among the many objectives of the trip was
        
        
          to identify launch sites with enough area to
        
        
          accommodate the drill and various support
        
        
          equipment necessary for completing the
        
        
          three lake crossings as specified in the drill
        
        
          plan.
        
        
          “Finding launch sites with enough flat
        
        
          area in close proximity to where we’d be
        
        
          drilling was a challenge,” Dagenhart says.
        
        
          “There are few areas of flat space desired
        
        
          for launch sites because the steep terrain
        
        
          is prevalent right up to the lake’s edge.
        
        
          All three bores were also situated near or
        
        
          alongside bridges, where the depth of the
        
        
          water averages from 90 ft (27.4 m) to more
        
        
          than 100 ft (30.5 m). Since we were required
        
        
          to maintain a 40 ft (12.2 m) clearance, the
        
        
          bores needed to reach a depth of 150 ft
        
        
          (45.7 m) very quickly; a challenging feat given
        
        
          the proximity of the launch sites to the
        
        
          lake’s edge.”
        
        
          The first bore, completed alongside the Niangua
        
        
          Bridge, consisted of a continuous 3500 ft (1066.8 m)
        
        
          shot that took just less than a month to complete.
        
        
          The second was a 3600 ft (1097.3 m) shot located near
        
        
          the Community Bridge. Just completed, the third and
        
        
          final lake crossing was a 6000 ft (1828.8 m) bore near
        
        
          Hurricane Deck where, coincidentally, a new bridge was
        
        
          also being built.
        
        
          “Construction of the new bridge, along with concerns
        
        
          levied by the bridge construction contractor involving the
        
        
          demolition of the old bridge, prompted an alteration to the
        
        
          tolerance,” Dagenhart says. “The specified tolerance on that
        
        
          bore was increased to 100 ft (30.5 m). As a result, the bore
        
        
          near the Hurricane Deck Bridge required reaching a depth
        
        
          of 278 ft (84.7 m) quickly.
        
        
          A 9 7/8 in. (25.1 cm) chisel bit with tungsten carbide
        
        
          inserts was chosen for all three bores. “We’ve found that
        
        
          once we encounter rock in excess of 6000 psi (413.7 bar),
        
        
          depending on the pipe we’re installing, bits with tungsten
        
        
          carbide inserts will last longer,” Dagenhart says. “This was
        
        
          important on a bore of this length, beneath the lake, that
        
        
          we not have to pull back and change a worn bit before
        
        
          completing the shot. Experience told us this was the type
        
        
          of bit we needed to use.”
        
        
          In addition to the limited space for establishing a launch
        
        
          site and strict tolerances required in the drill plan, the hard
        
        
          rock – much of which is fractured in gravel, cobble and
        
        
          some limestone – presented additional challenges for the
        
        
          Lone Star drill team. Given the tough conditions, Dagenhart
        
        
          has been pleased with the average daily production rates
        
        
          by the D1000x900 drill of approximately 300 ft (91.4 m)
        
        
          per day. “If we can average 10 pipe joints a day, we’re very
        
        
          happy,” he says.
        
        
          Back reams were not necessary on the first bore,
        
        
          although, on the Community Bridge crossing, where the
        
        
          drill plan specified 8 in. dia. (20.3 cm) steel pipe versus the
        
        
          Figure 2.
        
        
          Lone Star Directional Drilling works on three trenchless bores on the
        
        
          Summit project near the Lake of the Ozarks. The three bores are located beneath
        
        
          the lake at sites alongside three major bridges in the area.
        
        
          118
        
        
          
            World Pipelines
          
        
        
          /
        
        
          JUNE 2015